Project Exploration Earthworks Buldania Lithium JV

Client Mineral Resources Limited

Location Approx. 30 km east of Norseman, WA

Duration March – July 2023

Project Summary

Yilgarn Contracting constructed drill pads, sumps, and access tracks, in preparation for an exploration drilling program. 

Our activities included:

  • Utilising GPS D8T Dozers and GPS Cat 336 Excavators to complete precise earthworks.
  • Ensuring drill pads and access tracks were constructed with minimal environmental impact in strict compliance with site disturbance permits.

Achievements

A challenge in this project was adhering to the site disturbance permits, which mandated minimal working areas to construct drill pads and access tracks. Our team employed strategic planning and precise execution to meet these requirements while effectively supporting the exploration efforts.